GSB material: gradings I to VI, tests and laying under MoRTH Clause 401

GSB is usually ordered by its initials alone. MoRTH Clause 401 holds six gradings, and a stack that passes Grading I cannot pass Grading V: the two do not overlap on the 0.425 mm sieve.

By SM Infra7 min read

In short

  • GSB is granular sub-base: the first granular layer of a road, laid on the sub-grade under MoRTH Specifications for Road and Bridge Works, Fifth Revision (2013), Clause 401.
  • Table 400-1 gives six gradings, and the contract names which one. III and IV are limited on only four sieves. V and VI are low-fines drainage gradings.
  • Table 400-2 sets the stone: impact value 40 maximum, liquid limit 25 maximum, plasticity index 6 maximum, CBR 30 minimum at 98% dry density unless the contract says otherwise.
  • It is compacted to at least 98% of MDD (IS 2720 Part 8) at 1 to 2 percent below OMC, up to 200 mm a layer with a vibratory roller.
  • Most GSB trouble is fines: too many and the layer holds water, too few and it will not compact.

A purchase order that reads GSB and a tonnage leaves out the one thing the plant needs to know. Granular sub-base under MoRTH Clause 401 is six different gradings, and material blended for one will not necessarily pass another.

GSB stands for granular sub-base. It is the first granular layer of a road, laid on the compacted sub-grade and under the wet mix macadam, and it does two jobs: it spreads load onto the soil and lets water out of the pavement. The MoRTH Specifications for Road and Bridge Works, Fifth Revision (2013), give six gradings in Table 400-1 and the physical tests in Table 400-2. Your contract says which grading applies.

What GSB is made of and where it sits

Clause 401 allows natural sand, crushed gravel, crushed stone, crushed slag, or a combination. Brick metal, kankar and crushed concrete are permitted in the lower sub-base only. On a highway package fed by a crusher it is crushed stone: coarse fractions and crusher fines blended until the mix sits inside the specified envelope. The same material goes into haul roads, yards and working platforms, as the materials page lists. The layers of a highway pavement shows the whole stack.

The six gradings in Table 400-1

Each figure is percent by weight passing that IS sieve. Read down a column, not across.

MoRTH Table 400-1, Gradings I to III (percent passing)
IS sieveGrading IGrading IIGrading III
75.0 mm100--
53.0 mm80-100100100
26.5 mm55-9070-10055-75
9.50 mm35-6550-80-
4.75 mm25-5540-6510-30
2.36 mm20-4030-50-
0.85 mm---
0.425 mm10-1510-15-
0.075 mm<5<5<5

A dash means the table sets no limit on that sieve for that grading.

MoRTH Table 400-1, Gradings IV to VI (percent passing)
IS sieveGrading IVGrading VGrading VI
75.0 mm-100-
53.0 mm10080-100100
26.5 mm50-8055-9075-100
9.50 mm-35-6555-75
4.75 mm15-3525-5030-55
2.36 mm-10-2010-25
0.85 mm-2-10-
0.425 mm-0-50-8
0.075 mm<5-0-3

Only Grading V uses the 0.85 mm sieve, and it has no limit at 0.075 mm.

Gradings I and V are identical from 75 mm down to 9.5 mm and then part company: I wants 10 to 15 percent passing 0.425 mm, V allows 0 to 5. Gradings III and IV are limited on four sieves only, so they run coarse and open.

Which grading goes where

Two documents speak to this, in different words. MoRTH Clause 401.2.1 says Gradings III and IV should preferably be used in the lower sub-base, and Gradings V and VI as a sub-base-cum-drainage layer. IRC:37-2018 says in Clause 7.2.1 that the drainage layer is Grading III or IV and the filter or separation layer is Grading I, II, V or VI. Where the GSB is 200 mm or less, a single drainage-cum-filter layer of Grading V or VI serves.

Physical requirements in Table 400-2

MoRTH Table 400-2: physical requirements for GSB
PropertyRequirementTest
Aggregate impact value40 maximumIS 2386 Part 4 or IS 5640
Liquid limit25 maximumIS 2720 Part 5
Plasticity index6 maximumIS 2720 Part 5
CBR at 98% dry density30 minimum, unless the contract specifies otherwiseIS 2720 Part 16

The printed table lists IS 2720 Part 5 against CBR, which looks like a misprint. The CBR method is Part 16.

Where water absorption (IS 2386 Part 3) is above 2 percent, Clause 401.2.2 asks for the wet aggregate impact value to IS 5640, and soft aggregates such as kankar, brick ballast and laterite are tested wet as well. Older site notes quote a ten percent fines value for GSB. It is not in the Fifth Revision's table. Aggregate tests for highway work explains what each test measures.

Laying and compaction

  • Moisture. At compaction the material should be 1 to 2 percent below OMC.
  • Roller. Up to 100 mm compacted thickness may be rolled with a smooth-wheeled roller of 80 to 100 kN. A single compacted layer of up to 200 mm needs a vibratory roller of 80 to 100 kN static weight. Roller speed is not to exceed 5 km/h.
  • Density. At least 98% of maximum dry density by IS 2720 Part 8.
  • Two layers. Where GSB is laid as upper and lower sub-base, each layer is not less than 150 mm (Clause 401.2.1). IRC:37-2018 Clause 7.2.2 puts separate drainage and filter layers at a minimum of 100 mm each and a single filter-cum-drainage layer at 150 mm.

GSB is measured in cubic metres, finished in position, and the plant sells it in tonnes. The quantity of GSB and WMM in a kilometre of road shows the arithmetic between the two.

Test frequency and level tolerance

Minimum checks on GSB (MoRTH Tables 900-3 and 900-1)
CheckMinimum frequency or limit
GradationOne test per 400 m3
Atterberg limitsOne test per 400 m3
Moisture content before compactionOne test per 400 m3
Density of compacted layerOne test per 1,000 m2
Surface level±10 mm

Levels are checked on a grid 6.25 m along the road by 3.5 m across. In any 10 consecutive readings only one may be outside tolerance, and by not more than 5 mm.

What goes wrong at the plant

Nearly always, fines. Too many and the layer holds water, the opposite of what a sub-base is for. They usually arrive with the feed: weathered seams, overburden not stripped clean, a wet face. Clay in that fraction pushes the plasticity index past 6 before the grading looks wrong. Too few fines and the layer stays bony: it will not close under the roller, and the density test fails.

The control is in two places. Screen deck apertures decide what each fraction contains, and the blend proportion decides what the stack contains. Grading V is not Grading II with less dust added by eye: 0 to 5 percent passing 0.425 mm means the fine fraction has to be screened out, and a lower deck that blinds in damp weather puts it straight back. On our crushing plants a change of specified grading is a change of decks, about a shift of work.

Then the stockpile. A conical stack segregates as it is built, coarse to the toe and fines in the core, so a loader working only the edge sends out something the lab never sampled. Reading a sieve analysis explains how to tell a plant fault from a sampling fault.

Standards and sources

  • MoRTH Specifications for Road and Bridge Works, Fifth Revision (2013), Section 400, Clause 401, Tables 400-1 and 400-2
  • MoRTH Specifications for Road and Bridge Works, Fifth Revision (2013), Section 900, Tables 900-1 and 900-3
  • IRC:37-2018 Guidelines for the Design of Flexible Pavements, Clauses 7.2.1 and 7.2.2
  • IS 2720 (Part 8): 1983, heavy compaction; IS 2720 (Part 16): 1987, CBR; IS 2386 (Parts 3 and 4); IS 5640
  • Plant practice on deck changes: SM Infra's own operating record

Your contract and its technical schedules override anything written here. Check the clause before you build to it.

Asked on site

Quick answers

01What is the full form of GSB in road construction?

GSB stands for granular sub-base. It is the first granular layer of a flexible pavement, laid on the compacted sub-grade and below the wet mix macadam. In MoRTH's Specifications for Road and Bridge Works it is covered by Clause 401, with the gradings in Table 400-1.

02What is the difference between GSB Grading I and Grading V?

Both have a 75 mm top size and identical limits down to the 9.5 mm sieve. They differ at the fine end. Grading I requires 10 to 15 percent passing 0.425 mm. Grading V allows only 0 to 5 percent there, adds a 2 to 10 percent limit at 0.85 mm, and is a sub-base-cum-drainage grading under MoRTH Clause 401.2.1.

03Is GSB paid for in tonnes or in cubic metres?

Under Clause 401 the layer is measured in cubic metres, finished in position, so the contractor is paid on compacted volume. A crusher sells by the tonne on a weighbridge slip. Reconciling the two takes the compacted density your site lab has measured for that material.

Get a rate

Need crushing on your site?

Four things and we can quote it. Send it before 6pm on a working day and you will hear back the same day.

Where · What · How much a month · When