CBR explained: the test, the number and what it does to pavement thickness

CBR is one number from a plunger pushed into a soaked sample. It decides how much stone goes under the bitumen, which is why a point or two on the sub-grade is worth arguing about before the borrow area is fixed.

By SM Infra7 min read

In short

  • CBR is the load needed to push a 50 mm plunger 2.5 mm or 5 mm into a soil specimen, as a percentage of the load for the same penetration in a standard material (IS 2720 Part 16). Design uses the value after four days of soaking.
  • IRC:37-2018 says the effective sub-grade CBR should be more than 5% for roads carrying over 450 commercial vehicles a day. The 8% figure belonged to the 2012 edition.
  • A weaker sub-grade means thicker granular layers, and so more GSB and WMM to crush and haul for every kilometre.
  • GSB has a CBR requirement of its own: a minimum of 30 at 98% dry density under MoRTH Table 400-2, unless the contract says otherwise.

Ask a pavement designer what the ground is like and the answer comes back as a CBR. The California Bearing Ratio is a penetration test: a 50 mm diameter plunger is pushed into a compacted soil specimen at 1.25 mm a minute, and the load it takes is expressed as a percentage of the load the same penetration takes in a standard material. A soil with a CBR of 6 resists the plunger 6% as well as the standard does.

The number matters because the pavement is sized on it. Under IRC:37-2018 the strength of the sub-grade, together with the traffic, sets how thick the layers above must be. Lower CBR, more stone.

How the test is done

The method is IS 2720 Part 16. Soil is compacted into the CBR mould at the density and moisture it will have in the road; for design, IRC:37-2018 Clause 6.2 asks for specimens remoulded at placement density and OMC. The specimen is soaked for 96 hours so that it is tested close to its worst condition. Then the plunger is driven in and the load is read at set penetrations from 0.5 mm to 12.5 mm.

Two readings give the result. The load at 2.5 mm is compared with a standard load of 1,370 kg, and the load at 5 mm with 2,055 kg. Usually the 2.5 mm value governs. If the 5 mm value comes out higher and stays higher on a repeat, the 5 mm value is taken.

What the number says about a soil

CBR is a strength index, not a fixed property of the soil like its grading. The same soil gives different values at different densities and moisture contents, so the test condition has to be stated with the result. An unsoaked CBR on a dry-season sample can look far better than the soil will perform in August.

Compaction moves the value too. A sub-grade rolled to 97% of MDD carries a higher CBR than the same soil left a few points short, one more reason sub-grade compaction is tested as hard as it is.

Reading a soaked CBR
Soaked CBRWhat the soil is likeWhat it means for the pavement
Low: 5% or lessPlastic clays and silts that soften badly when wetShort of what IRC:37-2018 wants as effective sub-grade CBR on roads over 450 CVPD. Improve it or replace it
Moderate: above 5% and up to 15%Sandy and gravelly soils, good select borrowThe range the IRC:37-2018 design catalogues cover. Higher in the range means thinner granular layers
High: 30% and aboveWell-graded crushed or natural granular materialSub-base class. MoRTH Table 400-2 asks GSB for a minimum of 30 at 98% dry density

The bands are a reading aid, not a classification from any code. Only the figures 5%, 15% and 30 come from the documents named.

How sub-grade CBR enters pavement design

IRC:37-2018 defines the sub-grade as the top 500 mm below the pavement, compacted to at least 97% of MDD on expressways, national and state highways and other heavily trafficked roads (Clause 6.1). For high-volume roads the design CBR is the 90th percentile of the soaked test values (Clause 6.2): a conservative figure, not the average.

The design does not use the sub-grade value alone. Clause 6.4 asks for an effective CBR: a single equivalent value for the 500 mm sub-grade together with the embankment soil beneath it, worked out through the IITPAVE software. A strong select sub-grade over a weak embankment is credited with less than its own test value. The effective CBR is then converted to a resilient modulus in MPa: 10 times CBR up to a CBR of 5%, and 17.6 times CBR to the power 0.64 above that, capped at 100 MPa.

Then the provision most often misquoted. Clause 6.4.3 says the effective sub-grade CBR should be more than 5% for roads carrying more than 450 commercial vehicles a day, two-way, in the year of construction. The 8% minimum still quoted in site offices was the wording of IRC:37-2012, which the 2018 edition superseded. Codes are revised and the contract governs, so check which edition your agreement names.

Why a weak sub-grade costs aggregate

Every layer of a flexible pavement exists to spread the wheel load until the soil at the bottom can carry it. The weaker the soil, the more spreading is needed, and the granular layers do most of that work cheaply. So for the same traffic, a design on a low effective CBR carries a thicker sub-base and base than a design on a high one.

A thicker granular layer across a four-lane carriageway, for the length of a package, is a large tonnage to quarry, crush and haul. How much GSB and WMM a kilometre needs shows how fast thickness turns into tonnes, and it is why the sub-grade CBR in the design report deserves a second look before the material requirement is frozen.

Improving a weak sub-grade

  • Better borrow. Bring select soil for the top 500 mm from a source that tests higher. MoRTH Clause 903.2.2 asks for one CBR test, the average of three specimens, per 3,000 m3 of borrow from each source.
  • Stabilisation. Mixing lime or cement into the soil raises its strength and cuts its sensitivity to water. The dosage is a laboratory design, not a site guess.
  • Drainage. A sub-grade that stays dry performs above its soaked value. Side drains that work, and a sub-base that passes water out to the edge, protect the number the design assumed.
  • Compaction to specification. The cheapest improvement is reaching the 97% the design already counted on.

The CBR requirement for GSB

CBR is not only a sub-grade test. MoRTH Table 400-2 requires granular sub-base material to have a CBR of at least 30 at 98% dry density (IS 2720 Part 8), unless the contract specifies otherwise. A grading that passes the sieves but carries too many plastic fines can fail it, which is why the same table limits the liquid limit to 25 and the plasticity index to 6. GSB gradings and tests under Clause 401 covers the rest.

For a crusher operator that puts the CBR on the commissioning sample alongside the grading. For the earthwork crew it means knowing the sub-grade's figure before the first layer goes over it, because after that the only way to change it is to dig.

Standards and sources

  • IS 2720 (Part 16):1987, laboratory determination of CBR
  • IRC:37-2018, Guidelines for the Design of Flexible Pavements (Fourth Revision), Clauses 6.1, 6.2 and 6.4
  • IRC:37-2012 (superseded), for the earlier 8% sub-grade provision
  • MoRTH Specifications for Road and Bridge Works, Fifth Revision (2013): Table 300-2, Table 400-2 and Clause 903.2.2

Your contract and its technical schedules override anything written here. Check the clause before you build to it.

Asked on site

Quick answers

01What is the full form of CBR?

CBR stands for California Bearing Ratio. It is a penetration test that rates the strength of a sub-grade soil or granular material as a percentage of a standard material's resistance, and in India it is carried out under IS 2720 Part 16. Flexible pavement design under IRC:37-2018 starts from the soaked CBR of the sub-grade.

02What is the difference between soaked and unsoaked CBR?

A soaked CBR is tested after the compacted specimen has stood in water for 96 hours. An unsoaked CBR is tested as moulded. Soaking lets the soil take up water and soften, so the soaked value is lower. IRC:37-2018 bases design on the four-day soaked value because the sub-grade has to carry traffic through its wettest season.

03What is the minimum CBR of sub-grade for a national highway?

IRC:37-2018 Clause 6.4.3 says the effective sub-grade CBR should be more than 5% for roads with more than 450 commercial vehicles a day in the year of construction, which takes in national highways. The often-quoted 8% comes from the superseded 2012 edition. A contract can set a higher figure, and then that figure governs.

Get a rate

Need earthwork on your site?

Four things and we can quote it. Send it before 6pm on a working day and you will hear back the same day.

Where · What · How much a month · When